OutMazed Design
↑ Get Quote Start a chat
Open-plan office seen across wood-tone desks, with light grey vertical slat partitions framing a grey door with an exit sign, marble-look floor tiles, a printer on a wood-tone cabinet at the left and a dark slatted coffee corner between tall white units at the right, Project Door Step, Silicon Oasis
Guide · Dubai

Restaurant fit-out approvals in Dubai: the sequence explained

A restaurant or cafe unit in Dubai does not open on the strength of a finished interior. Between the handover of the keys and the first service there is a sequence of consents, each with its own reviewer, and the order you take them in decides whether the kitchen is built once or twice. This guide sets out that sequence for an operator: the landlord's fit-out guide and NOC, the authority for the building works, fire and life safety, the food safety review, signage, the trade licence and the completion certificate.

Free site visit · Approvals handled by us · Designed in 3D

WHY THE

Why the sequence matters more for a food unit

An office fit-out in Dubai answers to the landlord, the authority for the plot and Dubai Civil Defence. A restaurant or cafe answers to all of those and, in general terms, to the food safety and licensing bodies as well. The extract route decides where the cooking line can go; the cooking line decides where the suppression goes; the suppression and the hygiene review decide what the ceiling and walls are made of. Taking the steps out of order is how a kitchen gets built twice, in a city where rent often starts before the business can trade and a mall restricts contractor hours. Our guide to the commercial fit-out process in Dubai covers the stages every leased unit goes through; this page follows the approvals a food outlet adds. Our restaurant and hospitality fit-out team plans the dining room, the counter and the back of house together and applies for the approvals the job needs.

STEP ONE:

Step one: the landlord's fit-out guide and NOC

The building's consent usually comes before anything goes to an authority, and for a food unit the building's rules are often the tightest. In a mall or a tower the landlord typically issues a fit-out guide and reviews the drawings before giving its no-objection certificate; our page on the building management and community NOC explains that consent and why there is no single Dubai-wide version of it.

  • Read the fit-out guide before the lease is signedIt tells you whether the unit has a kitchen extract riser, where a grease interceptor can sit, and what the base build provides for gas, water and cooling. A former shop or office may have no extract route at all, and that is a lease question rather than a design question.
  • What the guide tends to coverWorking hours, protection of the common areas, the route for deliveries and waste, the materials allowed on the shopfront, the ceiling zone the landlord keeps for its own services and the drawings it wants to see.
  • What the NOC application needsTypically a layout, a services plan showing extract, gas, drainage and cooling loads, a shopfront elevation and the contractor's details. The landlord's consent is often needed before the authority permit can be applied for, which is why it goes first.
  • Outlets inside hotelsA restaurant inside a hotel may answer to the operator's technical team as well as the owner; where the operator has design or technical standards the design is drawn to meet them, as on our hospitality interior design page.
STEP TWO:

Step two: the authority with jurisdiction for the building works

Which authority depends on the plot, not the business

Dubai has several bodies that regulate building work, and the plot the unit sits on decides which one reviews the fit-out. Dubai Municipality, according to its own description, has laid down procedures for issuing building permits and completion certificates. In the zones regulated by the Dubai Development Authority, fit-out and modification works need a DDA permit, and DDA lists an NOC from the building owner among the documents; our page on DDA approval for fit-outs covers where it applies. Within the jurisdiction of the Ports, Customs and Free Zone Corporation, Trakhees reviews design and drawings before fit-out works start and inspects them after they finish; see our Trakhees approval page. Where a free zone has its own building authority, that body's guidance applies.

For a restaurant this review generally reads the layout, the partitions, the structure wherever anything is cut or cored for the extract and the drainage, the MEP drawings and any change to the shopfront. Drawing the kitchen in detail now, rather than as a hatched box labelled kitchen, saves a resubmission if the extract route or the drainage later needs a change the permit did not cover. We confirm which authority applies at the free site visit and apply for the permit ourselves; our fit-out and renovation approvals page sets out the kinds of approval that exist.

Workstation row under an exposed ceiling with linear lights, ending at a door with an exit sign, Project Design, Silicon Oasis
Workstation row under an exposed ceiling with linear lights, ending at a door with an exit sign, Project Design, Silicon Oasis
STEP THREE:

Step three: Dubai Civil Defence for fire and life safety

Fire and life safety sits with Dubai Civil Defence, which refers to the UAE Fire and Life Safety Code of Practice as the guide for its requirements. Our page on Dubai Civil Defence approval covers the services DCD lists. In general terms, these are the parts of a restaurant a fire and life safety review tends to look at.

01

Kitchen suppression

A cooking line with open flame or hot oil is commonly expected to carry a suppression system over the hood, linked to the gas and power supply, so the hood and the equipment list are fixed before the fire drawings are completed.

02

The extract and fresh-air route

The extract runs through the building to a discharge point the landlord allows, with fire dampers where it crosses compartments. In Dubai's heat the make-up air has to be cooled as well, so the fresh-air route and the cooling load are checked together.

03

Exits and travel distances

A dining room with fixed banquettes, a bar counter and a kitchen behind it still has to keep clear exit routes, exit signs and door widths, so the furniture is drawn in before the fire drawings are submitted.

04

Materials, the ceiling and the alarm

Wall linings, ceiling panels, insulation and the finishes near the cooking line may be reviewed for fire performance, and the unit's detection, alarm and emergency lighting tie into the building's own system. Choose the decorative ceiling after the fire drawings are approved, from what the approval allows.

05

Inspection before completion

DCD approval rarely stands alone. DDA, for example, states that a DCD completion certificate is required before its own fit-out completion certificate, so where that rule applies the DCD inspection is planned ahead of the building authority's.

STEP FOUR:

Step four: food safety, signage and the trade licence

These reviews run alongside the building and fire approvals, and an office fit-out never meets them. They are described in general terms only; the authority's own guidance applies, and your licensing body sets the order in which it wants its documents.

  • The food safety reviewIn general terms, the kitchen layout, the finishes and the hygiene arrangements of a food outlet are reviewed by the food safety authority against its own published requirements. The design is usually expected to show the flow from delivery to service, separation between raw and cooked work, hand-wash points, washable surfaces, pest-resistant detailing and the waste route.
  • Finishes that pass and finishes that do notHygiene reviewers generally look for surfaces that can be cleaned: coved junctions between floor and wall, sealed joints, impervious wall finishes behind the cooking line and the wash-up, and ceilings that do not shed. Exposed timber, open-grained stone and fabric belong in the dining room, and Dubai's dust makes open shelving in a store a cleaning problem as well. Agree the line where dining-room finishes stop and kitchen finishes start.
  • Signage and the shopfrontThe external sign and any change to the shopfront usually go through the landlord's design review and may need the authority's signage approval as well. Mall guides often fix the sign zone, the illumination and the materials, so the sign is ordered after the drawings are approved.
  • The trade licence and its timingThe licensing authority for the unit, mainland or free zone, issues the trade licence that names the activity, and the approvals are generally expected to match the activity and the address on it. Some steps may need the licence, or whatever preliminary consent your licensing body issues, in hand; others can run on the lease and the landlord's consent. Check with your licensing body which it wants first.
  • The completion certificate and handoverOnce the works are inspected, the building authority issues its completion certificate and the landlord takes its own handover of the unit. The licensing and food safety bodies take their own final step from there. Build the opening date from this certificate, not from the day the furniture arrives.
WHAT THE

What the drawings must show for these reviews

One set of drawings answers every reviewer

Every reviewer reads the same set of drawings, so the set is prepared to answer all of them at once: the kitchen layout with every piece of equipment and its services; the extract hood, the duct route and the discharge point; the fresh-air and cooling plan, sized for a Dubai summer; the grease interceptor and where it can be reached for cleaning; the floor drains and their falls; the cold room and the dry store; washrooms with hand-wash points; the accessible route from the entrance to a table; and the exits, with the furniture drawn in. A restaurant is a working kitchen with a dining room attached, and our restaurant and cafe interior design starts from that kitchen and the service route before the dining room is drawn.

The services are where the sequence most often breaks. Extraction, fresh air, gas, drainage and power are located to suit the equipment layout before ceilings and floors are finished, and the equipment list comes from the operator's kitchen supplier, so we ask for it early. The inspections check that every drain, outlet and grille is where the approved drawings show it, and a change of equipment after approval may have to go back through the reviewers, so freeze the list before the first submission.

Coffee corner set into grey vertical slatted wall panels, with a floating shelf and tall white units at either side, Project Door Step, Silicon Oasis
Coffee corner set into grey vertical slatted wall panels, with a floating shelf and tall white units at either side, Project Door Step, Silicon Oasis
COMMON MISTAKES,

Common mistakes, and the order that avoids rework

Many delays in a Dubai restaurant fit-out come from doing a sensible thing at the wrong moment. These are the places where the order usually breaks.

01

Signing a lease without an extract route

A unit with no extract riser, no gas and nowhere for a grease interceptor can still be let for a restaurant. Check before you sign; if the unit is a bare shell, our guide to Cat A and Cat B handover explains what the landlord does and does not provide.

02

Designing the dining room first

The kitchen is squeezed into what the dining room leaves; the reviewers read it the other way round. Fix the kitchen, the extract and the washrooms, then design the room; our restaurant and cafe design ideas cover the room once that is done.

03

Ordering and booking the opening before approval

Counters, back bars, the cooking line and the sign are built to the approved drawings, so ordering them earlier means altering what has been made. The opening date follows the completion certificate, and the inspections that lead to it follow finished services.

04

Splitting the job between a designer and a builder

Each handover between firms is a chance for the approved drawings and the work on site to drift apart. Our commercial fit-out runs design, approvals and building under one project manager, so the approved set is the built set.

WHO APPLIES

Who applies for what

We apply for the approvals our fit-outs need: the landlord's NOC, the building authority permit, the Dubai Civil Defence approvals and the further approvals a food outlet usually needs. The operator provides what only the operator can: its licence and company documents, the lease, the kitchen equipment list from its supplier and the signatures the applications call for. Which approvals apply depends on the location, the building and the type of business, so we confirm the list at the free site visit and tell you what we need from you. Check the order of your licensing body's own steps with that body; we build the programme around it.

FAQ

Questions and answers

Which approval comes first for a restaurant fit-out in Dubai?

The landlord's or the mall's. Its fit-out guide sets the rules and its no-objection certificate is often needed before the authority permit can be applied for.

Which authority reviews the building works?

It depends on the plot, not the business: Dubai Municipality, the Dubai Development Authority in the zones it regulates, Trakhees within the jurisdiction of the Ports, Customs and Free Zone Corporation, or a free zone's own building authority inside that zone. We confirm which one at the site visit.

Does a cafe without a cooking line still need Dubai Civil Defence approval?

In general terms, fire and life safety applies to the unit whether or not it cooks: exits, detection, alarm, emergency lighting and materials are still reviewed. Suppression and the extract route come in once there is a cooking line.

What does the food safety review look at?

In general terms, the kitchen layout and the flow of food through it, the separation of raw and cooked work, hand-wash points, washable floors and walls, pest-resistant detailing and the waste route. The authority's own guidance sets the detail.

Do I need the trade licence before the fit-out starts?

Some steps may need the licence or your licensing body's preliminary consent in hand and others can run on the lease and the landlord's consent, and the order differs between mainland and free zone jurisdictions. Check with your licensing body which it wants first.

Who applies for the approvals?

We apply for the approvals our fit-outs need ourselves, from the drawings we produce. You provide the licence documents, the lease, the kitchen equipment list and the signatures the applications call for.

How long do restaurant fit-out approvals take?

It depends on the location, the building, the scope and how complete the first submission is. A set of drawings that answers every reviewer at once helps, and we give a programme after the site visit.
GUIDES

More guides

SERVICES

Our related services

CONTACT US

Contact Us

Ready to bring
your vision to life?

Get in Touch

We appreciate your interest in OutMazed ® Design and would be delighted to assist you with your design requirements. Our team of professionals are committed to providing you with the highest standard of service and satisfaction possible.

Please feel free to contact us and let us know what you're interested in or looking for. We are here to assist you whether you need help with a new project, renovation, or just some design advice. Fill out the contact form below, and one of our staff will contact you as soon as possible.

Alternatively, you can also reach us via phone or email, and our friendly staff will be happy to help you. We encourage you to take the first step towards transforming your space with OutMazed ® Design by contacting us today.